LocationNameEquipment SupplierStatusPercentage completionCurrent Expenditure exc VatProject Budget Exc VatEst Completion DateWayforward
HARDAP REGIONAMALIA DAMHardcore MiningCompleted on 22/02/2024100%1,400,000.001,700,000.0020/02/2024Fully Completed
HARDAP REGIONSOUTSPOET DAMHardcore MiningOn going20%400,000.001,700,000.0026/03/2024Site Establishment
KHARAS REGIONKLEIN VALGRAS DAMOasis Capitalon going90%1,337,464.631,700,000.0029/02/2024on schedule
OSHIKOTO REGIONONAMULUYA DAMArtiflex Engineeringon going60%806,000.001,700,000.0015/03/2024Behind schedule
OHANGWENA REGIONODIMBO-OKAHENGE DAMDeni Building & Constructionon going90%1,380,852.801,700,000.0023/02/2024On schedule
HARDAP REGION - AMALIA DAM
KHARAS REGION - KLEINVALGRAS DAM
OSHIKOTO REGION - ONAMULUYA DAM
OHANGWENA REGION - ODIMBO-OKAHENGE DAM
HARDAP REGION-SOUTSPUT DAM